FMEA (Failure Mode and Effects Analysis) — a method for analyzing potential process or product failures and their consequences. It helps determine in advance what could go wrong, what the consequences would be, and what measures should be taken.
What FMEA is used for
The analysis is conducted during product development and modification, production preparation, and the improvement of existing processes. DFMEA examines design failures, while PFMEA examines process failures. The work is performed by a team of specialists who understand the subject of the analysis.
How the analysis works
- Define the function. What should the product or process do?
- Analyze the failure. What could go wrong, and what are the causes and consequences?
- Evaluate the current controls. What prevents the error and helps detect it?
- Assign actions. Record the measures, owners, and deadlines.
- Verify the result. Reassess the ratings after the actions have been completed.
It is important to distinguish three concepts. A failure is what was not performed; a consequence is what it led to; a cause is why it happened. For example: the wrong material was supplied; production was delayed; a different specification was selected when the order was prepared.
Risk assessment
Three risk ratings
S — severity of consequences
O — frequency of occurrence of the cause
D — ability of the current controls to detect the problem
In commonly used scales, a high D indicates poor detectability. The criteria and scales must be agreed upon before the work begins.
The Risk Priority Number, RPN, is calculated as S × O × D. It helps compare entries but is not the probability of failure. The same product can conceal different combinations of ratings, so critical consequences must not be ignored because of a low RPN.
How does AP differ from RPN?
The AIAG–VDA approach uses an Action Priority, AP, determined by the combination of S, O, and D. This is a separate logic, not a renaming of RPN. When working with a specific guideline, use that guideline’s criteria. Overview of the differences: ASQ’s practical guide to FMEA.
Training example: a procurement request
Below is a hypothetical example of applying the method to an office process. It illustrates the reasoning logic rather than providing a ready-made risk assessment for an organization.
| Analysis field | Example entry |
|---|---|
| Function | Transmit an approved material requirement to Procurement. |
| Potential failure | The request specifies the wrong material specification. |
| Consequence | Unsuitable material is purchased; the department’s work is delayed. |
| Cause | The author copied the data from an outdated document. |
| Current control | The approver manually cross-checks the description against the attachment. |
| Proposed action | Select the material from a directory of current specifications and save the document version in the request. |
| Result verification | Submit test requests, check that outdated specifications are blocked, and analyze any exceptions identified. |
How will the RPN change after the actions?
Suppose the team assigned S = 7, O = 4, and D = 6 using its ten-point scale. Then RPN = 168. After implementing and verifying the measures, it reasonably reassessed O as 2 and D as 3: the new RPN = 42. These figures are for training purposes; they cannot be transferred to a real process without an assessment. Severity S remains 7 because the consequences of the error itself have not changed.
How to organize the first working meeting
For a pilot analysis, select one segment: from creating the request to sending the order to the supplier. Invite the request author, the approver, and a procurement specialist. Prepare several anonymized examples of errors and the current instructions. During the meeting, review each transfer of information and record specific measures with owners and deadlines.
The result should be a working table with clear actions. It is better to replace the wording “strengthen control” with a verifiable task, for example: “prohibit sending a request without a valid specification; test this on five pre-prepared erroneous requests.” The number of examples here is hypothetical—the team determines whether the verification is sufficient, taking the risk into account.